A Hybrid optimization model for biomass trigeneration plant location: the Case of the City of Petrinja, Croatia
A Hybrid optimization model for biomass trigeneration plant location: the Case of the City of Petrinja, Croatia // Proceedings of 4th International Conference on Sustainability Science and Engineering / Cabezas, Heriberto (ur.).
Balatonfüred, Mađarska, 2015. (poster, međunarodna recenzija, sažetak, znanstveni)
CROSBI ID: 784617 Za ispravke kontaktirajte CROSBI podršku putem web obrasca
Naslov
A Hybrid optimization model for biomass trigeneration plant location: the Case of the City of Petrinja, Croatia
Autori
Dominković, Dominik Franjo ; Ćosić, Boris ; Perković, Luka ; Ban, Marko ; Duić, Neven
Vrsta, podvrsta i kategorija rada
Sažeci sa skupova, sažetak, znanstveni
Izvornik
Proceedings of 4th International Conference on Sustainability Science and Engineering
/ Cabezas, Heriberto - , 2015
Skup
4th International Conference on Sustainability Science and Engineering
Mjesto i datum
Balatonfüred, Mađarska, 26.05.2015. - 29.05.2015
Vrsta sudjelovanja
Poster
Vrsta recenzije
Međunarodna recenzija
Ključne riječi
trigeneration; location optimization; absorption; pit thermal energy storage; net present value
Sažetak
In this paper, optimization of the location of biomass trigeneration power plant was considered. The system combined biomass cogeneration power plant, absorbers and the seasonal pit thermal energy storage. Several factors influence merit of potential locations, which was shown in the different case studies for the City of Petrinja, Croatia. When the biomass availability, capacity of the power plant or the number of power plants changes the optimal location also change. Furthermore, economic assessment of choosing optimal and non-optimal location was performed. Case studies have shown that significant amount of yearly spending on fuel (biomass) can be avoided, if the optimal location has been chosen for the power plant location. Moreover, it was shown that while choosing the optimal location of the power plant, economic figures such as net present value (NPV) can be satisfying for the potential investor in the trigeneration power plant even in residential area.
Izvorni jezik
Engleski
Znanstvena područja
Strojarstvo
POVEZANOST RADA
Projekti:
120-1201918-1920 - Racionalno skladištenje energije za održivi razvoj energetike (Duić, Neven, MZOS ) ( CroRIS)
Ustanove:
Fakultet strojarstva i brodogradnje, Zagreb