Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard


Mesić, Miroslav; Tešnjak, Sejid; Skok, Srđan
Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard // Second IASTED Africa Conference
Gaborone, Bocvana, 2008. (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)


CROSBI ID: 365572 Za ispravke kontaktirajte CROSBI podršku putem web obrasca

Naslov
Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard

Autori
Mesić, Miroslav ; Tešnjak, Sejid ; Skok, Srđan

Vrsta, podvrsta i kategorija rada
Radovi u zbornicima skupova, cjeloviti rad (in extenso), znanstveni

Skup
Second IASTED Africa Conference

Mjesto i datum
Gaborone, Bocvana, 08.09.2008. - 10.09.2008

Vrsta sudjelovanja
Predavanje

Vrsta recenzije
Međunarodna recenzija

Ključne riječi
Auxiliary DC Installation; Failure; Reliability and Security

Sažetak
Due to failures of auxiliary DC installations outages of power plants and substations and degradation of reliability and security of power system in the past occurred. The auxiliary DC installation in switchyard has been calculated based simplified stationary model. New standard 61660-1 had been published 1997 and it was significant improvement of conditions related to dimensioning and analyzing auxiliary DC installation. That standard related to calculation of short circuit current took into account not only resistances, but inductances and capacities of all auxiliary DC installation components as well as the active alternative current network in front of the rectifier. In the past it was recorded numerous failures of auxiliary DC installation and it was reason for reconstruction of the most jeopardized DC subsystems. After reconstructions old and nonselective existing auxiliary DC installations and construction of DC subsystems in new switchyards respected of new criteria and IEC 61660-1 reliability and security of these switchyards and whole power system had been improved. However standard IEC 61660-1 should be changed from the reasons of new technology of components and new input data relevant for correct dimensioning and analyzing of auxiliary DC installation.

Izvorni jezik
Engleski

Znanstvena područja
Elektrotehnika



POVEZANOST RADA


Projekti:
036-0361557-1561 - Vođenje elektroenergetskog sustava u uvjetima tržišta električne energije (Tešnjak, Sejid, MZO ) ( CroRIS)

Ustanove:
Fakultet elektrotehnike i računarstva, Zagreb

Profili:

Avatar Url Srđan Skok (autor)

Avatar Url Sejid Tešnjak (autor)


Citiraj ovu publikaciju:

Mesić, Miroslav; Tešnjak, Sejid; Skok, Srđan
Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard // Second IASTED Africa Conference
Gaborone, Bocvana, 2008. (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)
Mesić, M., Tešnjak, S. & Skok, S. (2008) Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard. U: Second IASTED Africa Conference.
@article{article, author = {Mesi\'{c}, Miroslav and Te\v{s}njak, Sejid and Skok, Sr\djan}, year = {2008}, keywords = {Auxiliary DC Installation, Failure, Reliability and Security}, title = {Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard}, keyword = {Auxiliary DC Installation, Failure, Reliability and Security}, publisherplace = {Gaborone, Bocvana} }
@article{article, author = {Mesi\'{c}, Miroslav and Te\v{s}njak, Sejid and Skok, Sr\djan}, year = {2008}, keywords = {Auxiliary DC Installation, Failure, Reliability and Security}, title = {Disturbance in the Power System Caused by Auxiliary DC Installation Failure of Switchyard}, keyword = {Auxiliary DC Installation, Failure, Reliability and Security}, publisherplace = {Gaborone, Bocvana} }




Contrast
Increase Font
Decrease Font
Dyslexic Font