Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation


Dukić, Darko; Marić, Tamara; Babić, Dubravka
Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation // Proceedings of the ITI 2007 / Luzar-Stiffler, Vesna ; Hljuz Dubric, Vesna (ur.).
Zagreb: Sveučilišni računski centar Sveučilišta u Zagrebu (Srce), 2007. str. 107-112 (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)


CROSBI ID: 355618 Za ispravke kontaktirajte CROSBI podršku putem web obrasca

Naslov
Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation

Autori
Dukić, Darko ; Marić, Tamara ; Babić, Dubravka

Vrsta, podvrsta i kategorija rada
Radovi u zbornicima skupova, cjeloviti rad (in extenso), znanstveni

Izvornik
Proceedings of the ITI 2007 / Luzar-Stiffler, Vesna ; Hljuz Dubric, Vesna - Zagreb : Sveučilišni računski centar Sveučilišta u Zagrebu (Srce), 2007, 107-112

ISBN
978-953-7138-09-7

Skup
29th International Conference “ Information Technology Interfaces”

Mjesto i datum
Dubrovnik, Hrvatska; Cavtat, Hrvatska, 25.06.2007. - 28.06.2007

Vrsta sudjelovanja
Predavanje

Vrsta recenzije
Međunarodna recenzija

Ključne riječi
computer simulation ; project scheduling ; decision-making ; analysis of duration ; cost estimate ; triangular distribution ; statistical analysis

Sažetak
Computer simulation has found its place in the field of construction project management as well. Its usage in solving the scheduling problem can significantly enhance the project manager's decision-making, especially in today's complex operating conditions. The model of analysis of duration and cost estimate of construction projects, as presented in this paper, is based on a computer simulation. The theoretical framework for generating random numbers has been laid down by the triangular distribution. A key role in the model is played by statistical analysis whose usage ultimately results in establishing an appropriate confidence interval for the mean project duration.

Izvorni jezik
Engleski

Znanstvena područja
Informacijske i komunikacijske znanosti



POVEZANOST RADA


Profili:

Avatar Url Tamara Marić (autor)

Avatar Url Darko Dukić (autor)

Avatar Url Dubravka Babić (autor)


Citiraj ovu publikaciju:

Dukić, Darko; Marić, Tamara; Babić, Dubravka
Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation // Proceedings of the ITI 2007 / Luzar-Stiffler, Vesna ; Hljuz Dubric, Vesna (ur.).
Zagreb: Sveučilišni računski centar Sveučilišta u Zagrebu (Srce), 2007. str. 107-112 (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)
Dukić, D., Marić, T. & Babić, D. (2007) Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation. U: Luzar-Stiffler, V. & Hljuz Dubric, V. (ur.)Proceedings of the ITI 2007.
@article{article, author = {Duki\'{c}, Darko and Mari\'{c}, Tamara and Babi\'{c}, Dubravka}, year = {2007}, pages = {107-112}, keywords = {computer simulation, project scheduling, decision-making, analysis of duration, cost estimate, triangular distribution, statistical analysis}, isbn = {978-953-7138-09-7}, title = {Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation}, keyword = {computer simulation, project scheduling, decision-making, analysis of duration, cost estimate, triangular distribution, statistical analysis}, publisher = {Sveu\v{c}ili\v{s}ni ra\v{c}unski centar Sveu\v{c}ili\v{s}ta u Zagrebu (Srce)}, publisherplace = {Dubrovnik, Hrvatska; Cavtat, Hrvatska} }
@article{article, author = {Duki\'{c}, Darko and Mari\'{c}, Tamara and Babi\'{c}, Dubravka}, year = {2007}, pages = {107-112}, keywords = {computer simulation, project scheduling, decision-making, analysis of duration, cost estimate, triangular distribution, statistical analysis}, isbn = {978-953-7138-09-7}, title = {Analysis of Duration and Cost Estimate of Construction Projects Through Computer Simulation}, keyword = {computer simulation, project scheduling, decision-making, analysis of duration, cost estimate, triangular distribution, statistical analysis}, publisher = {Sveu\v{c}ili\v{s}ni ra\v{c}unski centar Sveu\v{c}ili\v{s}ta u Zagrebu (Srce)}, publisherplace = {Dubrovnik, Hrvatska; Cavtat, Hrvatska} }

Časopis indeksira:


  • Web of Science Core Collection (WoSCC)
    • Conference Proceedings Citation Index - Science (CPCI-S)
  • Scopus





Contrast
Increase Font
Decrease Font
Dyslexic Font