EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE


Inal, Fulya; Radujković, Mladen
EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE // Proceedings of 6th International Conference Organisation, Technology and Management in Construction / Radujković, Mladen ; Završki, Ivica (ur.).
Zagreb: Hrvatska Udruga za Organizaciju Građenja, 2003. str. 122-129 (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)


CROSBI ID: 177770 Za ispravke kontaktirajte CROSBI podršku putem web obrasca

Naslov
EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE

Autori
Inal, Fulya ; Radujković, Mladen

Vrsta, podvrsta i kategorija rada
Radovi u zbornicima skupova, cjeloviti rad (in extenso), znanstveni

Izvornik
Proceedings of 6th International Conference Organisation, Technology and Management in Construction / Radujković, Mladen ; Završki, Ivica - Zagreb : Hrvatska Udruga za Organizaciju Građenja, 2003, 122-129

Skup
6th International Conference Organisation, Technology and Management in Construction

Mjesto i datum
Mošćenička Draga, Hrvatska, 17.09.2004. - 20.09.2004

Vrsta sudjelovanja
Predavanje

Vrsta recenzije
Međunarodna recenzija

Ključne riječi
project life cycle; motorway construction project; construction equipment; equipment planning; resource planning

Sažetak
A motorway construction project can be characterized by a life cycle consisting of three phases: Design Phase, Implementation Phase and Operation phase. The first phase includes identification of needs, establishment of feasibility, preparation of proposal, estimation of resources that the organization is willing to commit development of basic budget and schedule, identification of project team and assignment of resources. Decision for equipment assignment for the motorway construction projects is an important part of the phase. This paper presents the Equipment Issues during Design phase of motorway construction project life cycle. Decision for equipment assignment is not only technical issue but also includes organizational, environmental, market and industry conditions. Several determinants have to be considered: • Determination of kind and size of equipment that might be used for the work. • Consideration of the money spent for equipment as an investment expecting to recover (with a profit), during useful life of equipment • Justification for rental equipment and equipment deliveries on time

Izvorni jezik
Engleski

Znanstvena područja
Građevinarstvo



POVEZANOST RADA


Projekti:
0082208

Profili:

Avatar Url Mladen Radujković (autor)


Citiraj ovu publikaciju:

Inal, Fulya; Radujković, Mladen
EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE // Proceedings of 6th International Conference Organisation, Technology and Management in Construction / Radujković, Mladen ; Završki, Ivica (ur.).
Zagreb: Hrvatska Udruga za Organizaciju Građenja, 2003. str. 122-129 (predavanje, međunarodna recenzija, cjeloviti rad (in extenso), znanstveni)
Inal, F. & Radujković, M. (2003) EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE. U: Radujković, M. & Završki, I. (ur.)Proceedings of 6th International Conference Organisation, Technology and Management in Construction.
@article{article, author = {Inal, Fulya and Radujkovi\'{c}, Mladen}, year = {2003}, pages = {122-129}, keywords = {project life cycle, motorway construction project, construction equipment, equipment planning, resource planning}, title = {EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE}, keyword = {project life cycle, motorway construction project, construction equipment, equipment planning, resource planning}, publisher = {Hrvatska Udruga za Organizaciju Gra\djenja}, publisherplace = {Mo\v{s}\'{c}eni\v{c}ka Draga, Hrvatska} }
@article{article, author = {Inal, Fulya and Radujkovi\'{c}, Mladen}, year = {2003}, pages = {122-129}, keywords = {project life cycle, motorway construction project, construction equipment, equipment planning, resource planning}, title = {EQUIPMENT ISSUES IN DESIGN PHASE OF MOTORWAY CONSTRUCTION PROJECT LIFE CYCLE}, keyword = {project life cycle, motorway construction project, construction equipment, equipment planning, resource planning}, publisher = {Hrvatska Udruga za Organizaciju Gra\djenja}, publisherplace = {Mo\v{s}\'{c}eni\v{c}ka Draga, Hrvatska} }




Contrast
Increase Font
Decrease Font
Dyslexic Font