Pregled bibliografske jedinice broj: 1149228

Analiza troškova i skraćivanje trajanja projekta u tehnici mrežnog planiranja pert/cost metodom


Barković, Dražen; Jukić, Josip; Blažević, Ivona
Analiza troškova i skraćivanje trajanja projekta u tehnici mrežnog planiranja pert/cost metodom // Interdisciplinary Management Research XIII
Opatija, 2017. str. 36-50 (predavanje, međunarodna recenzija, sažetak, ostalo)


CROSBI ID: 1149228 Za ispravke kontaktirajte CROSBI podršku putem web obrasca

Naslov
Analiza troškova i skraćivanje trajanja projekta u tehnici mrežnog planiranja pert/cost metodom
(Cost analysis and project duration shortening in network planning technique with pert/cost method)

Autori
Barković, Dražen ; Jukić, Josip ; Blažević, Ivona

Vrsta, podvrsta i kategorija rada
Sažeci sa skupova, sažetak, ostalo

Izvornik
Interdisciplinary Management Research XIII / - Opatija, 2017, 36-50

Skup
Interdisciplinary Management Research 2017

Mjesto i datum
Opatija, Hrvatska, 19.05.2017. - 21.05.2017

Vrsta sudjelovanja
Predavanje

Vrsta recenzije
Međunarodna recenzija

Ključne riječi
planiranje, upravljanje, trajanje projekta, troškovi
(planning, management, project duration, costs)

Sažetak
The process of planning and management is very complex in organizational systems in which also belongs an overhaul of complex technical systems (overhaul in the processing and chemical industry, repair of vehicles, machinery and equipment, ...). There are numerous examples of projects that have been called into question by reason of exceeding the set deadline of completion and thus the project price increase made this investment irrational even before the beginning of its implementation. Classical methods of planning and management are inadequate to such requirements of development so the technique of network planning has become an indispensable technique for planning and management of a very complex projects. The nature of such projects is not often compatible with the assumption of the estimated duration of activities and thus the total duration of the project as a deterministic size, so in such cases, the duration of the activity should be observed as random variables, to which should be adapted and the procedure for calculating time parameters. By using data from the existing technical documentation, available literature and practical experience, in this paper was made the analysis of duration time in relation to costs and cost analysis in relation to the duration of the project by using PERT / COST method.

Izvorni jezik
Engleski

Znanstvena područja
Ekonomija



POVEZANOST RADA



Citiraj ovu publikaciju:

Barković, Dražen; Jukić, Josip; Blažević, Ivona
Analiza troškova i skraćivanje trajanja projekta u tehnici mrežnog planiranja pert/cost metodom // Interdisciplinary Management Research XIII
Opatija, 2017. str. 36-50 (predavanje, međunarodna recenzija, sažetak, ostalo)
Barković, D., Jukić, J. & Blažević, I. (2017) Analiza troškova i skraćivanje trajanja projekta u tehnici mrežnog planiranja pert/cost metodom. U: Interdisciplinary Management Research XIII.
@article{article, author = {Barkovi\'{c}, Dra\v{z}en and Juki\'{c}, Josip and Bla\v{z}evi\'{c}, Ivona}, year = {2017}, pages = {36-50}, keywords = {planiranje, upravljanje, trajanje projekta, tro\v{s}kovi}, title = {Analiza tro\v{s}kova i skra\'{c}ivanje trajanja projekta u tehnici mre\v{z}nog planiranja pert/cost metodom}, keyword = {planiranje, upravljanje, trajanje projekta, tro\v{s}kovi}, publisherplace = {Opatija, Hrvatska} }
@article{article, author = {Barkovi\'{c}, Dra\v{z}en and Juki\'{c}, Josip and Bla\v{z}evi\'{c}, Ivona}, year = {2017}, pages = {36-50}, keywords = {planning, management, project duration, costs}, title = {Cost analysis and project duration shortening in network planning technique with pert/cost method}, keyword = {planning, management, project duration, costs}, publisherplace = {Opatija, Hrvatska} }




Contrast
Increase Font
Decrease Font
Dyslexic Font