SIGNIFICANCE OF 400 kV LINE NORTH-TO-SOUTH THROUGH B&H NETWORK TO CROATIAN POWER SYSTEM AFTER UCTE RECONNECTION
This study is initiated by HEP Transmission and Croatian Independent System and Market Operator (CROISMO). Its main objective is set as to recognise possible influence that 400 kV network in Bosnia and Herzegovina (B&H) may have on security and stability of Croatian (HR) power system after UCTE reconnection. Despite preliminary schedule of activities related to restoration of war damages in Croatian and B&H power systems, it is already clear that reconstruction activities in B&H network will be considerably late. Simultaneously, all planned reconstruction activities in Croatian power system are going well and according to the schedule will be finished till the end of year 2003.
transmission network; system security and stability; UCTE reconnection
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
Podaci o izdanju
Energetski institut 'Hrvoje Požar', Zagreb, Hrvatska
2003.
nije evidentirano
objavljeno