Method for Building Information Modeling Supported Project Control of Nearly Zero-Energy Building Delivery (CROSBI ID 284644)

Prilog u časopisu | izvorni znanstveni rad | međunarodna recenzija

Gumbarević, Sanjin ; Burcar Dunović, Ivana ; Milovanović, Bojan ; Gaši, Mergim Method for Building Information Modeling Supported Project Control of Nearly Zero-Energy Building Delivery // Energies (Basel), 13 (2020), 20; 5519, 21. doi: 10.3390/en13205519

Podaci o odgovornosti

Gumbarević, Sanjin ; Burcar Dunović, Ivana ; Milovanović, Bojan ; Gaši, Mergim

engleski

Method for Building Information Modeling Supported Project Control of Nearly Zero-Energy Building Delivery

With the increasing number of nearly zero- energy buildings (NZEB) due to increase of global awareness on climate change, the new concepts of design and control must be developed because of great NZEB dependency on detailing and multidisciplinary approach. This paper proposes a three-level gateway control method for NZEB project delivery by using digital representation of the building in building information modeling (BIM) environment. These controls (C1, C2 and C3) are introduced before three main phases of any project delivery—design phase, construction phase and handover. The proposed project control procedure uses black-box building energy modeling within the BIM environment, so the paper explores the reliability of one tool for direct energy modeling within the BIM- authoring software. The paper shows two types of validation tests with satisfactory results. This leads to conclusion that analyzed tool for energy simulation within BIM environment can be used in a way that is described in a proposed project control procedure. For further research it is proposed to explore reliability of tools for energy simulation connected to other BIM- authoring software, so this project control procedure could be independent of BIM-authoring software used in the paper.

nearly zero-energy building ; building information modeling ; project delivery ; project control ; building energy modeling

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

Podaci o izdanju

13 (20)

2020.

5519

21

objavljeno

1996-1073

10.3390/en13205519

Trošak objave rada u otvorenom pristupu

Povezanost rada

Građevinarstvo, Temeljne tehničke znanosti

Poveznice
Indeksiranost