Risk Management for Decommissioning of Fcilities - The DRIMA Approach (CROSBI ID 689395)
Prilog sa skupa u zborniku | prošireni sažetak izlaganja sa skupa | međunarodna recenzija
Podaci o odgovornosti
Kaulard, Joerg ; Francois, Patrice ; Ljubenov, Vladan ; Pennington, Mark ; O’Sullivan, Patrick ; Schruder, Kristan ; Škanata, Dejan
engleski
Risk Management for Decommissioning of Fcilities - The DRIMA Approach
In order to provide assistance and feedback on the application of risk management methodologies in preparation of and during decommissioning, IAEA’s International Decommissioning Network (IDN) launched in December 2012 the “Decommissioning Risk Management Project – DRiMa Project” which was completed in November 2015. The DRiMa project developed its own approach for risk management which inter alia distinguishes between the need to manage uncertainties associated with assumptions (related to initial decommissioning plans) or with strategic decisions (setting the frame for final decommissioning plans), and the need to manage (operational) risks associated with the detailed planning and implementation of decommissioning activities (project risks). Central elements within the DRiMa approach are the use of prompters to systematically analyze assumptions, strategic decisions and their uncertainties and (operational) risks and the use of registers to systematically manage these entities.
Nema
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
Podaci o prilogu
---.
2016.
objavljeno
Podaci o matičnoj publikaciji
Proceedings of the International Conference on Advancing the Global Implementation of Decommissioning and Environmental Remediation Programmes
Beč: IAEA-International Atomic Energy Agency
Podaci o skupu
International Conference on Advancing the Global Implementation of Decommissioning and Environmental Remediation Programmes
poster
23.05.2016-27.05.2016
Madrid, Španjolska